Bay Projects is proud to be part of the ongoing construction at various Murraysburg Windfarms, where significant progress is being made on foundation works. To date, 12 of 22 foundations have been excavated, with 8 already cast and advancing towards completion.

Our scope of work on this project includes:

  • Bulk excavation of approximately 1,500m³ per foundation
  • Placement of blinding concrete
  • Anchor cage assembly
  • Installation of 45 tons of reinforcing steel per foundation
  • Pouring of approximately 532m³ of concrete per foundation
  • Backfilling of around 900m³ per foundation